None of HDC's projects are currently on hold: Zuhair

"I can confidently announce that none of HDC's projects are on hold. This is not a small achievement, it is a major effort," said Zuhair.

Featured Image

Managing Director of the Housing Development Corporation (HDC) Ali Zuhair speaking at the ceremony to inaugurate the water theme park project in Hulhumale' -- Photo: Fayaz Moosa | Mihaaru

Umar Shan Shafeeq

2026-11-26 13:10:11

Managing Director of the Housing Development Corporation (HDC) Ali Zuhair has stated that none of HDC's projects are currently on hold, framing it as 'not a small achievement'.

During the ceremony to restart the water theme park hotel project in Hulhumale' which started in 2017 but had stalled later, Zuhair said that those projects are now ongoing because of the continued efforts of HDC staff and senior state officials.

"I can confidently announce that none of HDC's projects are on hold. This is not a small achievement, it is a major effort," said Zuhair.

As an example of such a project, Zuhair gestured to the city hotel project STO began developing in Hulhumale' in 2008 and the Reethigas Residence project. The vertical parking project, which had also stalled, is also ongoing, spoke Zuhair.

The water theme park project which has been restarted today has not seen any progress for 9 years, said Zuhair, adding that it was a project that had previously been deemed as not viable to move forward with.

A model of the Hulhumale' water theme park -- Photo: Fayaaz Moosa

"The practical efforts for the water theme park that have begun today is a project that has been on hold for 9 years from 2017. This is a book which has been closed after it was said it could not be done, and has been reopened upon a special initiative by President Dr. Mohamed Muizzu," continued Zuhair.

The Hulhumale' water theme park was a project that was started in 2017 during former President Abdulla Yameen's government which saw an expenditure of USD 25 million (MVR 385.5 million). The project was awarded at the time to Malaysian company Miri Housing Development for 35 years, but was abandoned later.

HDC filed a case to the Anti-Corruption Commission (ACC), citing acts of undue benefits when the project was being awarded to Miri Housing Development.

In September 2022, the High Court stopped HDC's decision to void the agreement surrounding the construction of the water theme park and the corporation's decision to reclaim the land the project was set to be constructed on. However, HDC appealed the case at the Supreme Court, with the court voiding the High Court's ruling in April 2023.

The case was filed to the High Court at the time after HDC voided the agreement they made with Waterfront Hotel and Leisure Pvt Ltd for the construction of a water theme park and a six-floor leisure hotel, with HDC informing the company to hand over the plot afterwards. Waterfront Hotel and Leisure Pvt Ltd filed a case in Civil Court, requesting an interim order to delay them having to comply with HDC's decision. However, the Civil Court ruled that they would be unable to grant their request. And so, Waterfront Hotel and Leisure Pvt Ltd went on to appeal the ruling at High Court.

HDC stated today that the project which was stalled for various reasons has been restarted under a completed and expansive master development plan that includes a world-class international resort hotel.

The project is split into two parts across a massive 41,549.70 square meter plot of land. The water theme park will be developed on a 17,800 square meter plot of land, and a resort hotel will be developed on a 23,749.70 square meter plot of land, said HDC.